Civic Issues
Topics getting the most attention in Carrboro public meetings, ranked by how frequently they are discussed.
2 issues in parks rec
Bolin Creek Greenway Crossing Analysis
The town council reviewed the crossing analysis for Phases 3 and 4 of the Bolin Creek Greenway, discussing the trade-offs between short low-profile bridges that create a flood rise and require a FEMA CLOMR versus expensive high-span bridges.
Bolin Creek Greenway Opposition
Engineers shared flood impact studies for pedestrian bridges along Phases 3 and 4 of the Bolin Creek Greenway. The council supported using shorter, lower bridges to keep costs down and minimize environmental clearing, with a strong focus on building Site 1 first.