Topics getting the most attention in Currituck County public meetings, ranked by how frequently they are discussed.
2 issues with critical priority
Moyock wastewater treatment plant expansion
The county committed up to $8.5 million to start building new drainage basins at the Moyock Regional plant, aiming for October 2026 completion and roughly 100,000 gallons per day of added capacity. Businesses waiting to hook up to sewer now have a date to plan around, with bigger expansions hinging on state and federal funding.
Mid-Currituck Bridge funding gap
The bridge faces a $700-800 million funding gap and federal grant denials tied to litigation. The ARPO votes April 15 on whether to keep the project committed or scale it to preliminary engineering only, which would free $173 million for other projects.