Proposed Data Center Regulations and Potential Moratorium

Summary

McMillan laid out a model moratorium work plan citing a 300-megawatt data center pre-application on Custer Avenue and limited water, sewer and power capacity. It was received as information; drafting comes next, and most public forum speakers demanded an actual moratorium.

At a glance

Total mentions
5
Last 30 days
2

Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.

Impact analysis

💰Financial impact

Unknown; focus on whether utility upgrades and PWC rate policy would shift costs to households.

✅Who benefits

Residents near the proposed Custer Avenue site and ratepayers concerned about footing infrastructure upgrade costs.

⚠️Who could be affected

Data center developers and proponents of immediate economic development face delayed approvals if a moratorium is adopted.

Mentions & discussions (6)

MeetingNov 2, 2026

City Council Work Session — November 2, 2026

McMillan laid out a model moratorium work plan citing a 300-megawatt data center pre-application on Custer Avenue and limited water, sewer and power capacity. It was received as information; drafting comes next, and most public forum speakers demanded an actual moratorium.

CityView NCOct 22, 2026

Fayetteville May Get a Data Center Moratorium After All

About two-dozen people, many with signs, opposed data centers and supported a moratorium during the Fayetteville City Council meeting on Monday, April 27, 2026. " data-large-file="https://i0.wp.com/www.cityviewnc.com/wp-content/uploads/2026/04/042726...

MeetingMay 4, 2026

City Council Work Session — May 4, 2026

Numerous residents urged the council during public comment to enact a formal one-year moratorium on data center development, citing severe threats to municipal water supplies, high electrical demand, and chemical pollution.

MeetingApr 27, 2026

City Council (Regular) — April 27, 2026

City Council established a 120-day study period and pause on data center applications to examine environmental, noise, and energy impacts.

ABC11 NewsApr 15, 2026

Fayetteville divided as data center debate intensifies

Fayetteville divided as data center debate intensifies ABC11 News

MeetingApr 13, 2026approved

City Council (Regular) — April 13, 2026

The city is grappling with how to regulate data storage facilities as interest grows. While staff proposed new zoning definitions, buffering, and noise controls, the Council voted to explore a temporary moratorium to allow for deeper study of environmental, water, and electrical impacts.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Fayetteville

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.