Summary
New water meters from Badger Meter, meter lids from Core & Main, tank recoating at the Ward plant and a clarifier rebuild at the Eastside plant were all on the consent agenda — routine but essential water system upkeep.
At a glance
- Total mentions
- 5
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.
Impact analysis
Roughly $1.1 million across the five utility purchases and contracts.
Water and sewer customers across the city.
None identified.
Mentions & discussions (5)
Regular Meeting of the High Point City Council - Nov 2, 2026
New water meters from Badger Meter, meter lids from Core & Main, tank recoating at the Ward plant and a clarifier rebuild at the Eastside plant were all on the consent agenda — routine but essential water system upkeep.
Finance Committee - Jul 30, 2026
The city approved several sole-source purchases totaling over $400,000 to repair electrical switchgear, replace air blowers, install sludge pumps, and buy nutrient analyzers for water and wastewater treatment plants.
Finance Committee - Apr 16, 2026
Following a chemical leak, the city is auditing electrical systems at the water treatment plant to prevent future disruptions.
Finance Committee - Mar 12, 2026
The city added $800,000 to an external maintenance contract to address high repair volumes caused by severe winter weather and ice storms.
Finance Committee - Jan 29, 2026
The city is spending $1.037 million with J. Cumby Construction to install a new emergency generator at the Oak Hollow raw water pump station to ensure water reliability during emergencies.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for High Point
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.