Medium PriorityParks Recopen

Stallings Chestnut Lane pedestrian partnership

Summary

Stallings wants to team up on two sidewalk projects along shared town limits — about $2.5 million total, split 50/50 (~$1.2–1.3M each). Building now costs about the same as waiting for federal money that wouldn't finish until 2033. Council said keep talking; final decision in July.

At a glance

Total mentions
2
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 8, 2026.