3 issues in water utilities with medium priority
Grove Street to Elizabeth Avenue Drainage Shift
The stalled Grove Street pump project's $207,655 in Golden LEAF money is going to the Elizabeth Avenue drainage project instead. Alderman Bryant spoke up for the Duffyfield/Grove Street neighbors who've flooded for years and wants the city to keep hunting money for them.
Water Fund SCADA Upgrade
The board moved $450,000 from the Water Fund to upgrade the SCADA system that monitors water and sewer operations, plus $40,000 for rising retiree insurance costs.
Pay-as-you-go utility program ends
Only 69 of 24,000 customers used the prepaid program, which cost about $60,000 a year. All users move back to standard billing April 1, with deposits and installment plans for those with arrears, plus $10,000 for the charity roundup fund.