Summary
Running the water plant 8-10 hours a day wastes up to 400,000 gallons per startup — potentially $500/day. Two more operators would allow 24-hour operation, less waste, and better cross-training.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Jul 23, 2026.
Impact analysis
Two recurring operator salaries offset by reduced water waste of potentially $500/day.
Water customers through less waste, better pressure reliability, and improved system oversight.
None identified.
Mentions & discussions (4)
Board of County Commissioners - Jul 23, 2026
Utilities Director James Proctor updated residents: land easement negotiations with Walmart for sewer access to Highway 210 are underway, NCDEQ review of the Mill Creek discharge is in progress, well-field bids are expected within 90 days, and service should be operational by late 2028 or early 2029.
Board of County Commissioners - Jun 15, 2026
Speaker after speaker pressed for extending water lines to residents without service; Commissioner Groves defended earlier statements that sparse lines can't cover their own cost.
Board of County Commissioners - May 4, 2026
Three public commenters and two commissioners raised water issues — from countywide 'water for all' to low pressure at 280 River Landing Drive in Maple Hill.
Board of County Commissioners - Mar 27, 2026
Running the water plant 8-10 hours a day wastes up to 400,000 gallons per startup — potentially $500/day. Two more operators would allow 24-hour operation, less waste, and better cross-training.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Pender County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.